Free English JOHN DEERE GREENSTAR 3 2630 (01) PDF document. Download the PDF, use the online viewer, or browse the FAQs for easy troubleshooting.


CLICK HERE TO DOWNLOAD JOHN DEERE GREENSTAR 3 2630 (01) PDF DOCUMENT

If this is not the document you want for this product, click here to see if we have any other documents for this product.


How to use the PDF below:
* Touchscreen: Swipe up/down with-in the PDF to scroll and pinch or spread with two fingers to zoom.
* Mouse: While your mouse is hovering over the PDF, use the mouse wheel to scroll and click on the – / + buttons at the bottom of the PDF to zoom.


How do I perform the initial General Documentation Setup using the Setup Wizard on the JOHN DEERE GREENSTAR 3 2630 Display?

To perform the General Documentation Setup using the Setup Wizard on the JOHN DEERE GREENSTAR 3 2630 Display:

Step 1. Select Menu.

Step 2. Select GreenStar.

Step 3. Select GreenStar Main.

Step 4. Select the Setup tab.

Step 5. Select the Documentation check box.

Step 6. Select Accept.

NOTE: Setup Wizard guides operator through the set up of resources, machines and implements, and operations.

Step 7. To navigate through Setup Wizard, press the following buttons on the right side of screen:

Exit Setup

Navigate to Next Page

Navigate to Previous Page

Press Accept twice when done


What selections are mandatory for documentation setup on the JOHN DEERE GREENSTAR 3 2630 Display?

Machine Type and Name, as well as Implement Type and Name, are mandatory input selections for documentation setup.


What is important to set for the Task selection to start documentation recording on the JOHN DEERE GREENSTAR 3 2630 Display?

To start documentation recording, the task needs to be set to any value other than “documentation off,” which is the factory default setting.


What are the mandatory selections for Resources on the JOHN DEERE GREENSTAR 3 2630 Display, and what happens if they are not set?

Client, Farm, and Field are mandatory selections. If selections are not set, documentation recording will not start.


What are the options available for setting the Recording Source on the JOHN DEERE GREENSTAR 3 2630 Display if it is not set to Auto?

If recording source is not set to Auto, the following options are available:

Manual: Press the button on display to start and stop documentation recording.

Implement switch 0: Documentation recording will turn on when switch is moved in default position.

Implement switch 1: Documentation recording will turn on when implement switch is moved out of default position.


What additional options might be available for setting the Recording Source on the JOHN DEERE GREENSTAR 3 2630 Display, and under what condition does recording start for these options?

Additional options might include:

Rear PTO: Recording starts when Rear PTO is switched on.

Front PTO: Recording starts when Front PTO is switched on.

Rear Hitch: Recording starts when Rear Hitch is lowered.

SCVs: Recording begins and stops when indicated SCV is moved.

NOTE: Any device not switched electronically, such as mechanical SCVs, cannot be found in this drop-down list. Options are only visible if machine supports these devices.


How is documentation recording determined by Offsets A, B, and C for an implement on the JOHN DEERE GREENSTAR 3 2630 Display?

Documentation recording takes place at Offsets A + B (sum of Offset A and Offset B). Offsets A, B, and C are the base for implement drawing on map.


Why is Offset D important for drawn implements on the JOHN DEERE GREENSTAR 3 2630 Display?

Offset D is important for drawn implements. It is needed for calculating the position of implements in curves.


What is the working width of an implement used for on the JOHN DEERE GREENSTAR 3 2630 Display?

The working width of the implement is needed to calculate how much area is worked and to display information on the map.


What are the required steps to set up Planting and Seeding without a prescription on the JOHN DEERE GREENSTAR 3 2630 Display?

For Planting and Seeding Without Prescription on the JOHN DEERE GREENSTAR 3 2630 Display:

Step 1. Select Seed Type. Seed Type is a crop that must be planted, such as corn, wheat, or barley.

A. Prescription indicates which prescription is selected.

B. Implement Name indicates which implement is selected.

Step 2. Select Target Rate (seed/area).

A. Select Rate Unit. Mass per area and seeds per area are available.

B. Select Rate. Seed Rate does not control seed rate of machine; it is for documentation purposes only.

C. Accept.

Step 3. Add Variety.

Step 4. Select Variety.

Step 5. Select Color.

Step 6. Accept. For each variety that needs to be planted in different row units, repeat steps 3-6.

Step 7. Assign variety to rows. Step 7 can be skipped if one variety is assigned to all rows.

a. Select Variety.

b. Select End Row.

c. Next.

d. Press Accept when all rows are assigned.


What is the requirement for using a Prescription when setting up Planting and Seeding on the JOHN DEERE GREENSTAR 3 2630 Display?

Prescription can only be used in combination with an implement capable of using prescriptions, such as John Deere sprayers or planters.


What are the key steps for setting up Planting and Seeding with a Prescription Created in Office Farm Management Software on the JOHN DEERE GREENSTAR 3 2630 Display?

To set up Planting and Seeding with Prescription Created in Office Farm Management Software on the JOHN DEERE GREENSTAR 3 2630 Display:

Step 1. Prescription

Step 2. Select Prescription.

Step 3. Enter Look Ahead time. Look Ahead time is the time needed to adjust to a new rate when driving from one rate area to the next. This value depends on the implement and the seeds applied.

Step 4. Accept.

Step 5. Verify Seed type.

Step 6. Verify Prescription.

Step 7. Verify implement name, indicating if the correct implement is used.

Step 8. Assign variety to rows. Step 8 can be skipped if one variety is assigned to all rows.

a. Select Variety.

b. Select End Row.

c. Next.

d. Press Accept when all rows are assigned.


What is mandatory input for Product Application-Single Product documentation recording on the JOHN DEERE GREENSTAR 3 2630 Display?

Product application describes what is done in the field. It is mandatory input for documentation recording.

The steps are:

Step 1. Select Product Application Type.

Step 2. Select single product from list.

Step 3. Add Product:

A. Select Product Type.

B. Select Product Name.

C. Select Rate Unit. If a John Deere or ISOBUS implement is connected, no input is needed if the selection is grayed out. Rate Unit is read from the implement and populated automatically.

D. Accept.

Step 4. Select Target Rate. Target Rate entered here is for documentation purposes only, and will not control Target Rate the implement actually applies. If a John Deere or ISOBUS implement is connected, no input is needed if the selection is grayed out. Rate Unit is read from the implement and populated automatically.


What are the steps to set up Product Application-Tank Mix documentation recording on the JOHN DEERE GREENSTAR 3 2630 Display?

For Product Application-Tank Mix:

Step 1. Select Product Application Type.

Step 2. Select Tank Mix from list.

Step 3. Add Carrier:

A. Select Carrier Type.

B. Select Base Solution Rate. If carrier is water, Base Solution Rate indicates how much water needs to be sprayed per area.

C. Select Rate Unit. If a John Deere or ISOBUS implement is connected, no input is needed if the selection is grayed out. Rate Unit is read from the implement and populated automatically.

D. Accept.

Step 4. Add Product:

A. Select Product Type.

B. Select Product Name.

C. Select Rate Unit. If a John Deere or ISOBUS implement is connected, no input is needed when the selection is grayed out. Rate Unit is read from the implement and populated automatically.

D. Select Rate. Rate entered here is for documentation purposes only, and will not control target rate which the implement actually applies.

E. Accept. Up to six different products can be selected. Repeat step 4 for each product, which should be applied.

F. Verify Target Rate. Sum up values of carrier and individual product to achieve the correct target rate. Target rate entered here is for documentation purposes only, and will not control target rate which the implement actually applies. If a John Deere or ISOBUS implement is connected, no input is needed if selection is grayed out. Target rate adjustments need to be made on the user interface of the implement.


What are the initial steps for Product Application-Prescription Created in Office Farm Management Software on the JOHN DEERE GREENSTAR 3 2630 Display?

For Product Application-Prescription Created in Office Farm Management Software:

Step 1. Prescription

Step 2. Select Prescription.

Step 3. Enter Look Ahead time. Look Ahead time is the time the implement needs to adjust to a new rate when driving from one rate-area to the next. This value depends on the implement and the seeds applied.

Step 4. Accept.

Step 5. Verify Prescription selected.

Step 6. Verify Prescription Rate, which indicates current rate applied.

Step 7. Move to”Product Application-Single Product” and “Product Application Tank” sections of this user guide to finish set up of product application operation.


What is the mandatory input for Harvest-Combine documentation recording on the JOHN DEERE GREENSTAR 3 2630 Display, and under what machine conditions is it possible?

Harvest describes what is done in the field. It is a mandatory input for documentation recording.

IMPORTANT: Harvest documentation is only possible with John Deere harvesting machines, such as cotton pickers, combines, and SPFH. If Harvest is selected on a tractor or any other machine type, documentation recording will not start.

The steps are:

Step 1. Change Harvest Settings.

Step 2. Select Crop Type.

Step 3. Select Variety.

Step 4. Check Variety Locator. If needed, check Variety Locator. Variety Locator requires a variety map, which needs to be imported from office desktop software.

Step 5. Press Accept.


What is important to know about individual load documentation for Harvest-Loads on the JOHN DEERE GREENSTAR 3 2630 Display?

Individual Load Documentation is only possible with John Deere harvesting machines, such as combines and SPFH.

To set up Load Documentation correctly:

Step 1. Define Load Name.

Step 2. Define Load Destination. If load name is enough information, load destination can be left blank.

Step 3. Auto Increment Load Number. When Auto Increment Load Number is checked, load will be saved and counted automatically every time unloading auger of combine is started. If this is not desired, do not check box. IMPORTANT: Auto Increment Load Number is only available on John Deere combines. It will not be available on other machines.


What is mandatory for Tillage documentation recording on the JOHN DEERE GREENSTAR 3 2630 Display?

Tillage describes what is done in the field. It is a mandatory input for documentation recording.

The steps are:

Step 1. Select Tillage Type. Tillage Type could be stubble breaking or seedbed preparation.

Step 2. Enter Tillage Depth. Tillage Depth is only documented by the 2630 display. It does not influence actual tillage depth.

IMPORTANT: If tillage is not selected, documentation recording will not start.


What is mandatory input for Other operation documentation recording on the JOHN DEERE GREENSTAR 3 2630 Display?

Operation describes what is done in the field. It is a mandatory input for documentation recording.

Step 1. Select Operation Type. Operation types include baling, mowing, and transport.

Step 2. Enter Operation Name. To locate an operation using office desktop software, use a meaningful name for the operation.

IMPORTANT: If operation is not started, documentation recording will not start.


How can I use the GreenStar Summary page on the JOHN DEERE GREENSTAR 3 2630 Display to check documentation setup?

The GreenStar Summary page is the easiest way to find missing data, such as field or machine information. It will show why documentation recording will not start.

To access the GreenStar Summary:

Step 1. Select Menu.

Step 2. Select GreenStar.

Step 3. Select GreenStar Main.

Step 4. Select Summary tab.

Step 5. Verify Client, Farm, Field, and Task setup. If Client, Farm, or Task show dashes “—-,” press on the area to open Resources page. On this page, setup can be made. Operator is not a mandatory input.

Step 6. Verify Machine, Implement 1, and Implement Width. If Machine or Implement 1 shows dashes “—-“, press on the area to open the Equipment page. On this page, setup can be made.

Step 7. Verify Operation. Check settings for the desired operation (Planting or Seeding, Product application, Harvest, Tillage, Other).

IMPORTANT: If there are dashes “—-” shown for any operation, documentation recording will not start. Press on the area to open “Documentation” page where setup can be made.

All other values shown on summary page are not mandatory input for documentation recording. Documentation recording will start even if inputs are not filled out.


How do I troubleshoot Harvest documentation issues using Diagnostics on the JOHN DEERE GREENSTAR 3 2630 Display?

To use Diagnostics for Harvest issues:

Step 1. Select Menu.

Step 2. Select GreenStar.

Step 3. Select Diagnostics.

Step 4. Select Recording.

Step 5. Verify the following settings:

Field defined: yes/no

Task defined: yes/no

Operations properly defined: Harvest: yes/no, N/A: —-

Recording space available: yes/no

GPS available: yes/no

Vehicle moving at minimum speed: yes/no

If all values show “yes” and recording still will not start, contact your John Deere dealer.

Step 6. Troubleshooting:

If Field defined or Task defined is “no,” refer to “Resources” section for correct setup information.

If “Harvest” under Operations properly defined is “no,” the display may indicate:

Mounted on a machine other than a John Deere harvest machine, such as cotton picker, combine, or SPFH. In this case, “Harvest” cannot be documented.

Set up incorrectly. To set up operation, refer to the Harvest Combine section.

If an operation is defined in addition to “Harvest,” recording will not start. To solve this issue, use the following steps:

a. Menu

b. GreenStar

c. Documentation

d. Operation tab

e. Remove

If Recording space available: no, copy data to a USB drive and delete documentation data of the display.

If GPS available: no, check connection to StarFire receiver and ensure it has clear view of sky. If this does not help, contact your John Deere dealer.

If Vehicle moving at minimum speed: no, accelerate machine until it is moving at minimum speed. For most applications, the minimum speed is 0.5 km/h (0.3 mph).

Selected recording source state: inactive and Documentation and coverage: inactive are inactive if coverage map is not painting. As soon as coverage map is painting, both of them are active.

Recording source: Auto. This is the recording source selected under “Equipment” in the GreenStar menu.


How do I troubleshoot Non-Harvest documentation issues using Diagnostics on the JOHN DEERE GREENSTAR 3 2630 Display?

To use Diagnostics for Non-Harvest issues:

Step 1. Select Menu.

Step 2. Select GreenStar.

Step 3. Select Diagnostics.

Step 4. Select Recording.

Step 5. Verify the following settings:

Field defined: yes/no

Task defined: yes/no

Operations properly defined:

Product application: yes/no

Planting/Seeding: yes/no

Tillage: yes/no

N/A: —-

Recording space available: yes/no

GPS available: yes/no

Vehicle moving at minimum speed: yes/no

If any of the values show “no” or recording source is not correct, continue to step 6.

If all values show “yes” and recording still will not start, contact your John Deere dealer.

Step 6. Troubleshooting:

If Field defined or Task defined is “no,” refer to “Resources” section in this user guide for more correct setup information.

If there is a “no” for an operation under Operations properly defined, the operation is not set up completely. Refer to “Operation-[specific operation to be performed]” section of this user guide to set up the operation correctly.

If Recording space available: no, copy data to a USB drive and delete documentation data of the display.

If GPS available: no, check connection to the StarFire receiver. Ensure clear view of sky or contact your John Deere dealer.

If Vehicle moving at minimum speed: no, accelerate machine until it moves at minimum speed. For most applications, the minimum speed is 0.5 km/h (0.3 mph).

Selected recording source state: inactive.

Documentation and coverage: inactive. “Documentation and Coverage” shows current recording state. “Inactive” means coverage map is not painting and recording is “off.”

Recording source: —-. This is the recording source selected under “Equipment” in the GreenStar menu.


CLICK HERE TO DOWNLOAD JOHN DEERE GREENSTAR 3 2630 (01) PDF DOCUMENT


Leave comments, questions, reviews, tips, tricks, hacks or page errors below. Account not required.